The scale and pace of construction LDS is impressive: the governor highlighted the course of work on the new ice arena

Anonim
The scale and pace of construction LDS is impressive: the governor highlighted the course of work on the new ice arena 1208_1

A year ago, February 7, a thousandth pile was installed on the construction site of the construction of a new ice isna in Novosibirsk. Today, concrete works are already held at the level of the upper floor of the building - at an altitude of 32 meters (the overall height of the object is 38.2 meters). Governor Andrei Heroven held a visiting meeting at the construction site of the multifunctional ice arena on Nemirovich-Danchenko Street in Novosibirsk.

The region's chapter reported: the installation of metal ceiling farms began. The length of the smallest mounted farm is 58.25 meters, weight - 75 tons. If the first farm builders mounted one crane, then for the installation of subsequent structures, two synchronized cranes is required. The weight of the design is such that one crane simply will not be able to raise it. Already in July, according to builders, the installation of metal structures will be completed, the total weight of which will be three thousand tons (2300 tons - on the main arena and 700 - in the training).

At the training ice arena, the installation of overlaps and facade structures was completed. The overall level of technical readiness of the object, taking into account material reserves at the construction site, equipment, materials under production and delivery, is 52 percent.

The head of the region noted that he was satisfied with the quality, the pace and the amount of work carried out: "Made everything to adjust the backlog that accumulated in the past pandemic year and break forward on those types of work that can be done now. For funding there is no doubt: funds in the federal and regional budgets are provided. Moreover, I note that we consider not the budgets of individual objects, and the budgets of a big construction, this huge construction site in the floodplain of the rivers, and by the redistribution of regional funds, close the timelines for financing the entire complex of objects that need to be completed to the World Hockey Championship 2023 , "Andrei herbalists emphasized.

The plans for 2021, the Minister of Construction of the Region, Ivan Schmidt, said, - close the thermal contour of the building and connect the arena to heat supply networks. This will allow in winter 2021-2022 to install internal engineering systems, continue the installation of equipment and proceed with finishing work.

"This ice isna refers to unique objects: here is large-spool metal structures, many monolithic works. Already "accepted" over 68 thousand cubic meters of concrete. By the end of March, we must finish the construction of the main building and climb the auxiliary constructions, such as stairwells, power floors, "said Denis Sinyuk, director for the construction of LLC EINALLF.

The facility can impress not only the scale of construction or the number of materials used for the construction of materials: in parallel several types of work are immediately.

"The processes are organized in parallel, so that we come to the heating season of this year with a closed circuit and eventually completed the construction of the object within the specified period. To date, the main types of work that we perform is monolithic structures, started installing metal structures, in parallel work on the construction of outdoor engineering networks is underway, since March we proceed to work on internal engineering networks. We also start working on a brickwork, "Denis Sinyuk listed.

Today, 400 people work at the construction site, with the opening of a new front of work, this quantity will increase. In the future - up to thousands of specialists.

The scale and pace of construction LDS is impressive: the governor highlighted the course of work on the new ice arena 1208_2

Novosibirsk manufacturers are involved in the construction of a large-scale, identification for the region of the object. For example, the facade structures that are already squeezed by the Arena building produces the Novosibirsk Company "Bearing Systems".

As part of a comprehensive plan for the preparation of the region to the MCHM-2023, it is building not only the multifunctional ice arena, on which the championship games will be held, but also a new metro station near her, five large road facilities with a total length of seven kilometers who will provide a convenient entrance to a new sports construction And they will increase the capacity of the highways of the Leninsky and Kirovsky districts of Novosibirsk (within the federal project "Safe and high-quality roads").

At the facilities of the transport infrastructure in two years - in the period 2019-2020 - the following types of work were carried out, Minister of Transport and Road Economy of the Novosibirsk Region Anatoly Kostylevsky reported to the Governor: Reconstruction of engineering networks; Device of storm sewage, armogarnet structures, earthlings, road clothing, asphalt concrete coating and lighting. Also erected pedestrian bridge supports. Currently, work on the installation and arrangement of the span structures of the bridge, concreting the walls of the underground transition; The pedestrian bridge will be ready for one hundred percent this year.

In addition, according to the minister, contracts were concluded for the manufacture and supply of high-barbecate equipment on the Damb of the October Bridge, elevator equipment for the pedestrian crossing through the dauber bridge, photovideo method systems for Lyschinsky Square.

LDS construction is under control of regional authorities.

For reference.

The construction of ice arena is carried out within the framework of the federal project "Sport - the norm of life" of the National Project "Demography". The six-storey complex of ice isna with a height of 38.2 meters and a total area of ​​55 thousand square meters. M provides for the main arena for 10.5 thousand spectators, the training arena with the stands for 200 spectators. Also here will be sports, gyms, sports locker rooms for teams, delegation offices and the necessary auxiliary premises. It is also planned to use ice arena as the main home stadium of the Siberia Hockey Club.

The project paid special attention to security issues and anti-terrorist protection. Security perimeter, inspection equipment for viewers and transport.

Taking into account the timing of the World Championship, the commissioning of multifunctional ice arena, infrastructure and landscaping objects is scheduled in 2022. The cost of the entire complex of work is estimated at 19.5 billion rubles, of which 10.5 billion rubles - the construction of LDS.

At the end of the autumn of 2019, the first piles were bare in the base of multifunctional ice arena and their tests were made confirming the safety of the projected design solutions.